Bastion Quay, Athlone – EV charging installation by GEV Technologies
    APARTMENT & MULTI-UNIT CHARGING

    All 51 parking bays made EV-ready — while maximising the SEAI grant

    Bastion Quay•Athlone
    0
    Bays cabled & charger-ready
    0
    Resident chargers live today
    0%
    SEAI grant secured on infrastructure
    0→100
    kVA supply — built to scale to 101 chargers

    THE CHALLENGE

    Bastion Quay is a 51-home development where every parking bay is allocated to a resident. As EV demand grew, the managing agent wanted charging available to anyone who needed it — without a disruptive install each time, and without paying for a supply upgrade the development didn't yet need.

    THE SOLUTION

    • Dedicated EV distribution cabinet on a new ESB supply, designed to upgrade from 50kVA to 100kVA as demand grows.
    • Full cabling to all 51 bays on day one, with a blank in every bay — the decision that drives the long-term economics.
    • Intelligent load & phase management sharing power dynamically across all three phases.
    • Smart app & billing platform — residents pay for what they use; the OMC carries no admin.

    THE RESULTS

    • All 51 bays charger-ready — the disruptive civils work is done once.
    • 13 chargers already live and in daily use by residents.
    • Maximum SEAI grant secured, with GEV handling the application for the OMC.
    • Adding the next charger takes minutes in a pre-cabled bay — and the supply is built to scale toward 101 chargers.
    Bastion Quay, Athlone – EV charging installation by GEV Technologies

    WHY THE APPROACH WORKS

    The costly part of apartment charging is the shared infrastructure, not the chargers themselves. By grant-funding that backbone once, cabling every bay up front and sizing the supply to grow, Bastion Quay turned a series of expensive one-off installs into a simple, low-cost upgrade path — with the SEAI grant covering most of the initial cost.

    Thinking about EV charging for your development?

    We survey your site, model the grant-funded cost and handle the SEAI application end to end.